Photo Gallery
5 Layer Line produces beautiful film. Generators get load tested. Full electrical by end of the month in new production and warehouse areas: Oct 2023
Walking Up The Completed Tower for 5-Layer: May 2023
Steel Has Arrived, 5-Layer Line Has Started: April 2023
Work on the Interior is Underway: March 2023
Continued Progress to Start the New Year: January 2023
Roof is Complete & Generators Installed: December 2022
Walls are Up & Roof Coming Soon: September 2022

Tip-Up Walls Going Up: August 2022
Pouring Foundation Concrete: July 2022
Foundation Work Has Begun: June 2022
Rolling in the Dirt and Preparing for Steel: May 2022
Weather Delays and Laying Concrete: March 2022
Beginning the Forming Process: March 2022
Houston Poly Expansion Begins: January 2022
Do you have a custom poly film, sustainable / biodegradable application, or flexible packaging project that requires uncompromising performance and exceptional customer service?
