5 Layer Line produces beautiful film. Generators get load tested. Full electrical by end of the month in new production and warehouse areas: Oct 2023

Walking Up The Completed Tower for 5-Layer: May 2023

Steel Has Arrived, 5-Layer Line Has Started: April 2023

Work on the Interior is Underway: March 2023

Continued Progress to Start the New Year: January 2023

Roof is Complete & Generators Installed: December 2022

Walls are Up & Roof Coming Soon: September 2022

Tip-Up Walls Going Up: August 2022

Pouring Foundation Concrete: July 2022

Foundation Work Has Begun: June 2022

Rolling in the Dirt and Preparing for Steel: May 2022

Weather Delays and Laying Concrete: March 2022

Beginning the Forming Process: March 2022

Houston Poly Expansion Begins: January 2022